    1 == Release 1 == 
     1== Time based releases == 
    22 
    3  1. Confirm OpenAL is buildable on Windows, or remove it from the list. 
    4  1. Construct generic unix installer. 
     3We want to do time-based rather than feature based releases. See for example [http://live.gnome.org/ReleasePlanning/TimeBased GNOME's info on time-based releases]. They've done this very successfully. 
     4 
     5== First major release, 2009.2.x == 
     6 
     7Proposed schedule for minor releases: 
     8 
     9 * 2009.2.0, Monday  4th May  
     10 * 2009.2.1, Monday  1st June  (4 weeks after .0)  
     11 * 2009.2.2, Monday 13th July  (6 weeks after .1) 
     12 
     13=== Remaining TODOs === 
     14 
    515 1. Upload .cabal file to Hackage 
    616   * No docs 
    7    * No tool dependencies that can be satisifed  
     17   * No tool dependencies that can be satisfied