Time based releases
We want to do time-based rather than feature based releases. See for example GNOME's info on time-based releases. They've done this very successfully.
First major release, 2009.2.x
Proposed schedule for minor releases:
- 2009.2.0, Monday 4th May
- Freeze for package changes for 2009.2.1: Monday 18th May
- 2009.2.1, Monday 1st June (4 weeks after .0)
- 2009.2.2, Monday 13th July (6 weeks after .1)
Remaining TODOs
- Upload .cabal file to Hackage
- No docs
- No tool dependencies that can be satisfied