Version 17 (modified by dons, 4 years ago)

--

Release timetable

We have said that major releases will be on a 6 month schedule. Major releases may include new and updated packages, while minor releases will contain bug fixes and fixes for packaging problems.

Second major release: 2010.2.0.0

A 4 month schedule for the second major release puts us in September.

2010.2.x will include GHC 6.12:

First major release, 2009.2.x

Schedule for minor releases:

  • 2009.2.0, Monday 4th May (actual release slipped by one day)
  • Freeze for package changes for 2009.2.0.1: Monday 18th May
  • 2009.2.0.1, Monday 1st June (4 weeks after .0)
  • 2009.2.0.2 delayed for 6.10.4 (releasd: Jul 16)
  • Freeze for package changes to 2009.2.0.2: Wednesday July 22
  • 2009.2.0.2, Wednesday July 29 (8 weeks after .1, originally planned for July 13, delayed due to GHC 6.10.4)